(Commonwealth Utilities Corp.) —  There will be scheduled power service interruptions on May 4 and 5, 2021, for customers in Papago.  The purpose of the scheduled power interruptions is for CUC to temporarily shut-off power in order for its linemen to safely replace existing rotted power poles to concrete poles in the affected areas. 

Tuesday, May 4

8:30 a.m. to 3:30 p.m.

• Outage Type: Sectionalized Interruption on the Feeder 4 Circuit 

• Project Location: Papago

• Power Service Areas Affected:

o From 8:30 a.m. to 1:30 p.m. — Isa Drive, Papago (Ahgaga Dr. & Amot Ln.)

o From 8:30 a.m. to 3:30 p.m. — Papago (parts of Isa Drive)

• Water Well Affected: None

• Wastewater Lift Station Affected: None

Wednesday, May 5

8:30 a.m. to 3:30 p.m.

• Outage Type: Sectionalized Interruption on the Feeder 4 Circuit 

• Project Location: Papago

• Power Service Areas Affected:  Papago (parts of Isa Drive)

• Water Well Affected: None

• Wastewater Lift Station Affected: None

CUC continues to work diligently to minimize any inconvenience to its customers.

 For more information, contact the CUC Customer Hotline (236-4333) or monitor its Facebook page (https://www.facebook.com/CommonwealthUtilitiesCorporation/).